TradeCalculator.co.uk
Paving Slab Calculator — Slabs, Sand & Cement
Calculate how many paving slabs you need plus the sharp sand and cement for a full sand:cement mortar laying bed. Standard UK slab sizes.
Length of the area to pave
Width of the area to pave
Area not a simple rectangle? An L-shaped area is just two rectangles: measure each one edge to edge and add it as a section. Use three sections for a T or U shape. The calculator adds every section together.
Adds 10% extra for cuts and breakages
10% standard, 15% for complex layouts
Enter your supplier price for a cost estimate
10mm (0.01m) standard gap between slabs
50mm (0.05m) standard mortar bed
Sharp/grit sand: 1.6 t/m³
Next up: related pages
How We Calculate This
Our paving slab calculator works out how many full slabs fit across the length and down the width of your area (allowing for the joint gap), rounds each direction up, then multiplies, so partial edge rows are counted as whole slabs to cut from. If the area is an L or T shape, add each rectangle as its own section: every section is counted as its own grid of whole slabs and the totals are added together (a cut cannot span the join), while the mortar bed uses the combined area.
The formula
Slabs across = round up [ Section length ÷ (Slab width + Joint width) ]
Slabs down = round up [ Section width ÷ (Slab height + Joint width) ]
Total slabs = round up [ (Slabs across × Slabs down, added over sections) × Wastage factor ]
Sand and cement for the mortar bed
Larger flags (600×600mm and up), wet-cast concrete and natural stone should be laid on a full sand:cement mortar bed per BS 7533-102:2025 — not loose sand. We split the bed volume by mix ratio (default 4:1 sharp sand to cement by volume) and convert each part to weight:
- Bed volume: Area × bed depth (50mm standard)
- Sharp sand: Bed volume × 4⁄5 × 1.6 t/m³ (sand fraction of a 4:1 mix)
- Cement: Bed volume × 1⁄5 × 1440 kg/m³ ÷ 25kg per bag (cement fraction)
- Joint width: 10mm standard (filled separately by pointing or kiln-dried sand — see FAQs)
For a 50mm 4:1 bed that is ≈ 64 kg sand + 14.4 kg cement per m². Use a 3:1 mix for vehicular loading. Loose sharp sand only suits small (≤450×450mm) calibrated pressed concrete flags.
Wastage
We recommend 10% wastage for straightforward layouts. An L or T shape entered as sections is already counted per section, so 10% still suits it. For areas with lots of cuts (curves, angled edges), increase to 15%. Paving slabs can break during cutting and handling, so always order extra.
Frequently Asked Questions
As an area-based estimate (with 10mm joints): 600x600mm slabs = approximately 2.8 per m², 450x450mm = approximately 4.7 per m², 400x400mm = approximately 5.9 per m², and 600x300mm = approximately 5.4 per m². These figures divide 1 m² by the slab-plus-joint footprint. The calculator counts physical slabs slightly differently — it works out how many full slabs fit across the length and down the width and rounds each up, because a partial edge row still needs a whole slab to cut from. So a 5m × 3m area in 600x600 returns 45 slabs (effectively 3.0/m²) rather than 42, before wastage. That edge rounding is deliberate and matches how you actually order. For indoor floor tiles, see our Floor Tile Calculator.
For 600x600mm and larger flags, wet-cast concrete slabs and all natural stone (Indian sandstone, limestone, granite), lay onto a full sand:cement mortar bed — not loose sand and not dot-and-dab blobs. This is the bedding method required by BS 7533-102:2025 and recommended by Pavingexpert: a solid, fully-supported bound bed resists frost heave, ground-water washout and rocking. A typical bed is 4:1 sharp (grit) sand to cement, 30-50mm thick on a compacted sub-base; use 3:1 for vehicular loading. Unbound loose sharp sand is only acceptable for small (450x450mm or smaller) calibrated pressed-concrete flags. Natural stone and porcelain should also be primed (SBR/cement slurry on the underside) for a full bond. Never use building (soft) sand — it goes fluid when wet and the slabs settle.
A 10mm joint (also called a gap or spacing) is standard for most paving slabs in the UK. This allows room for pointing with mortar (4:1 sand:cement mix) or kiln-dried sand. Wider joints of 15mm may be used with natural stone. Too narrow and pointing becomes difficult; too wide and it looks uneven.
Mortar pointing (4:1 sharp sand to cement) is the most durable option for patios and high-traffic areas. Brush-in kiln-dried sand is quicker but less durable and can wash out. Resin-based jointing compound is a modern alternative that sets hard but remains slightly flexible. Ensure your patio has the correct drainage fall — use our Drainage Fall Calculator.
Yes — always lay paving on a proper sub-base. Use 100mm of compacted Type 1 MOT sub-base for pedestrian areas, or 150mm for driveways — our Type 1 Sub-Base Calculator works out quantities. The sub-base goes down first, then a 30-50mm sand:cement mortar bed, then the slabs. For a gravel surface instead, see our Gravel Calculator.